Project Overview

Morse Consultants was appointed by Aspect Property Management to project manage the external repair and redecoration of the rear elevations of Goodwood Court in London.

Morse produced initial budgets for approval and a detailed specification of works to obtain competitive tenders. Morse also managed the works on-site which included slate-covered roof renewals, leadwork replacement, asphalt roof repairs and repairs to the brickwork elevations.

Services

Contract Administration

Aspect Property

Client: Aspect Property Management

Property: Goodwood Court

Contract: External Redecorations

Industry Sector: Residential - Multiple Occupancy

Contract Value: £110,000

Location: Devonshire Street, London

Duration on site: 9 weeks

Download Case Study



Case Study | Aspect Property Management

Project Overview

Morse Consultants was appointed by Aspect Property Management to project manage the external repair and redecoration of the front and rear elevations of 58 Eaton Place in the prestigious Belgravia area of London.

Morse produced initial budgets for approval and a detailed specification for the works to obtain competitive tenders. Morse also managed the works on-site which included a full roof covering replacement, timber repairs, lead work replacement, balcony, stonework and asphalt repairs and general redecoration.

Services

Contract Administration

Aspect Property

Client: Aspect Property Management

Property: 58 Eaton Place

Contract: External Redecorations

Industry Sector: Residential - Multiple Occupancy

Contract Value: £104,505

Location: Belgravia, London

Duration on site: 14 weeks

Download Case Study



Case Study | Aspect Property Management

Project Overview

Morse Consultants was appointed by Aspect Property Management to project manage the external repair and redecoration of the front and rear elevations of Goodwood Court in London. The works were split into two separate phases - the refurbishment of the rear of the property (Phase 1) was completed in November 2007 and the front elevations (Phase 2) in July 2010.

Morse produced initial budgets for approval and a detailed specification for the works to obtain competitive tenders. Morse also managed the works on-site which included slate-covered roof renewals, asphalt roof repairs, lead work replacement, timber repairs, stonework/brickwork repairs and general redecoration.

Services

Contract Administration

Aspect Property

Client: Aspect Property Management

Property: Goodwood Court

Contract: External Redecorations

Industry Sector: Residential - Multiple Occupancy

Contract Value: £200,000

Location: Westminster, London

Duration on site: 12 weeks per phase

Download Case Study



Case Study | Aspect Property Management

Project Overview

Morse Consultants was appointed by Aspect Property Management to project manage the external repair and redecoration of the front and rear elevations of Mall Chambers in London. The works were split into four separate phases - Phase 1 (25-48 Mall Chambers rear) was completed in August 2007, Phase 2 (1-24 Mall Chambers rear) was completed in August 2008, Phase 3 (1-24 Mall Chambers front) was completed in September 2009, and finally Phase 4 (25-48 Mall Chambers front) was completed in June 2010.

Morse produced initial budgets for approval and a detailed specification for the works to obtain competitive tenders. Morse also managed the works on-site which included slate-covered roof renewals, asphalt roof repairs, lead work replacement, timber repairs, stonework/brickwork repairs and general redecoration.

Services

Contract Administration

Aspect Property

Client: Aspect Property Management

Property: Mall Chambers

Contract: External Redecorations

Industry Sector: Residential - Multiple Occupancy

Contract Value: £200,000

Location: Notting Hill, London

Duration on site: 12 weeks per phase